State Development

Facilitating Economic and Regional Development

Government Goal

Future jobs and skills

Aim

Expand the road network in accordance with State and Commonwealth governments’ transport and land use strategies to support the state’s economic and regional development.

About the Program

The program includes most expansion, major infrastructure and bypass projects – predominantly the most complex works we deliver.

Key Performance Indicators
Target
Our target for the average return on which road and bridge construction expenditure will deliver future economic benefits to the community was exceeded and continues to improve

Our target for the average return on which road and bridge construction expenditure will deliver future economic benefits to the community was exceeded and continues to improve

We exceeded our contracts completed on time target and significantly improved on previous years
Contracts completed on budget exceeded our target and was higher than last year
  2018 2019 2020

Program expenditure $ million

467

618

461

Looking Ahead

Works planned for next financial year include:

  • commence construction of Albany Ring Road
  • continue development of Stage 4 of Karratha – Tom Price upgrading works
  • award and progress the Bunbury Outer Ring Road project
  • curve realignment South Western Highway Thompson Hill
  • begin construction of a second carriageway on Bussell Highway, Capel to Busselton
  • preconstruction works of Bussell Highway Stage 2, Hutton to Busselton
  • continue widening Kwinana Freeway northbound, Russell Road to Roe Highway
  • continue works on the Wanneroo Road and Joondalup Drive Interchange Project
  • continue construction of the Armadale Road Bridge – North Lake Road Flyover
  • progress the Karel Avenue duplication from Farrington Road to Berrigan Drive.

Some of these are already underway; visit the Projects and Initiatives section of our website to find out more.

Key Projects

Project Total Project
Cost
($ million)
2019–20
Cost
($ million)
Completion
Date
Description

Great Southern Region

Albany Ring Road
Stage 2

175.0

8.0

Late 2023

Construct and seal Albany Ring Road
Stage 2.

Metropolitan Region

Great Eastern Highway Upgrade – Bilgoman Road to Mann Street – Stage 2

40.3

6.7

October 2019

Widening to provide sealed shoulders and upgrade of intersections. Works included upgrade of drainage and street lighting and provision of pedestrian facilities (Kintore Road to Bilgoman Road – Stage 2).

NorthLink WA – Swan Valley Bypass –
Section 3

318.0

27.9

December 2019

Marella Road to Muchea – section 3.

Murdoch Drive Extension to Roe Highway at Kwinana Freeway

112.5

45.3

April 2020

Murdoch Activity Centre access with modifications to the Kwinana Freeway and Roe Highway interchange.

Kwinana Freeway Southbound – Manning Road On-Ramp

35.0

10.7

Late 2020

Provision of an on-ramp from Manning Road to Kwinana Freeway southbound. 

Pilbara Region

Onslow Road Phase 2

33.4

33.2

Mid 2020

Construction of Onslow Road and upgrade Phase 2.

Goldfields-Esperance Region

Coolgardie Esperance Highway – Emu Rocks

40.0

1.4

Early 2022

Upgrade 25 km section of highway including construction of passing lanes and widening and sealing shoulders.

Wheatbelt Region

Great Northern Highway – Walebing and Wubin sections

25.9

11.5

Late 2020

Construction of 4 km highway through Walebing.

Upgrade the intersection in Wubin to allow future southern access for 53.5 m road trains, access to local facilities and the Road Train Assembly Area.

Great Northern Highway – Bindoon Bypass section

275.0

1.6

Late 2020

Land definition and acquisition.

Kimberley Region

Broome Cape Leveque Road Upgrade

65.6

18.9

Late 2021

Reconstruction of carriageway and sealing of remaining unsealed section.

Gordon Duncan Road Upgrade

51.0

6.0

Late 2021

Road improvements to provide all weather access to two mines in Halls Creek area.

Aerial view of Northlink WA Read the story

State Development

WA’s Biggest Road Project Wraps Up