Operations

Road Efficiency

Providing Reliable and Efficient Movement of People and Goods

Aim

Improve the efficiency, capacity and utilisation of the existing road network as part of a total transport network.

The Program

The program includes projects that deliver geometric improvements, road widening, bridge strengthening and retrofitting to incorporate intelligent transport capabilities.

*For more detailed information on our Key Performance Indicators and targets see ‘Performance Measures’ 

  2019 2020 2021

Program expenditure $ million

411

563

589

Looking Ahead

Works planned for next financial year include:

  • continue construction of the Tonkin Gap project
  • continue development of the Pinjarra Heavy Haulage Deviation
  • continue development of EastLink WA, including funded grade separations at Drumpelier Drive, Altone Road and West Swan Road
  • commence construction of the Leach Highway and Welshpool Road interchange
  • continue development and construction of Great Eastern Highway Bypass interchanges with Abernethy Road, Lloyd Street and Roe Highway
  • commence construction of the Swan River Crossings project
  • continue construction of the widening of Mitchell Freeway southbound between Hodges Drive and Hepburn Avenue
  • continue works under the Traffic Congestion Management Program
  • complete construction of the Armadale Road Bridge – North Lake Road flyover
  • continue upgrading sections of Great Northern Highway through the Kimberley region
  • continue roundabout construction at the intersection of Great Northern Highway and Apple Street
  • continue delivering works on the Bunbury Outer Ring Road project.

Some of these are already underway; visit the Projects and Initiatives section of our website to find out more.

Aerial view of the Kwinana Freeway with the Swan River to the left Read the story

Road Efficiency

More Productive and Efficient Freeways

Key Projects

Project Total Project Cost
($ million)
2020–21
Cost
($ million)
Completion
Date
Description

Kimberley Region

Great Northern Highway – Ord River North

98.1

7.4

Late 2023

Road efficiency improvements to Ord River – Bow River.

Broome – Cape Leveque Road Upgrade

65.6

18.7

Late 2021

Construction and sealing of remaining
90 km long unsealed section.

Gordon Downs Road – Duncan Road Upgrade

51.0

10.2

Late 2023

Road improvements to provide reliable and safer, all-weather access to Aboriginal communities and a mine site.

Metropolitan Region

Leach Highway Carrington Street to Stirling Highway

76.0

33.6

Late 2021

Upgrade Leach Highway from Carrington Street to Stirling Highway.

Tonkin Highway – Collier Road to Stanton Road

290.0

65.9

Late 2023

Tonkin Gap Project – Collier Road to Stanton Road and associated works.

Great Eastern Highway Bypass Interchanges

320.0

2.1

Late 2024

Great Eastern Highway Bypass – Abernethy Road and Roe Highway interchange upgrades and associated works.

Pilbara Region

Great Northern Highway Koodaideri Road-over-Rail Bridge

24.7

8.7

December 2020

Construction of a single-span, road-over-rail bridge, inclusive of associated roadworks for the proposed Koodaideri mine rail track.

Port Hedland Spoilbank Marina Trucking Route

4.2

3.5

March 2021

Construction of Port Hedland Spoilbank Marina Trucking Route.

South West Region

Bussell Highway Widening Stage 1 and 2

85.0

24.9

Mid 2023

Construction of dual carriageway.

Bunbury Outer Ring Road Stage 2 and 3

852.0

77.8

Mid 2024

Construction of a high standard rural highway between Forrest Highway and Bussell Highway.

Wheatbelt Region

Great Northern Highway – Walebing and Wubin Sections

25.9

11.5

December 2020

Construction of 4 km highway through Walebing. Upgrade the intersection in Wubin to allow future southern access for 53.5 m road trains and access to local facilities.

Goldfields–Esperance Region

Coolgardie Esperance Highway – Emu Rocks South

52.0

2.2

Late 2022

Coolgardie Esperance Highway – Emu Rocks South reconstruction and passing lanes.