Community access
Improving community access and roadside amenity
Aim
Improve personal mobility and access needs on the road network.
About the program
The program provides infrastructure including remote access roads; access for walking and cycling; improved access and mobility for people with a disability; integrated public transport; and improved amenities such as information bays, noise attenuation and landscaping.
* For more detailed information on our Key Performance Indicators and targets visit here.
Target 90%
Community satisfaction with cycleways and pedestrian facilities slightly improved from last year result
Target 95%
Major flooding events across the State impacted on network availability however, the result was higher than last year
Target 90%
Contracts completed on budget was within target and higher than last years' result
Program expenditure $ million | 2022159 | 2023230 | 2024345 |
Iconic bridge set to transform pedestrian
and cyclists journeys
- Safer journey for more than 3,000 cyclists and pedestrians per day
- Iconic design incorporates Whadjuk Noongar culture and heritage
- Includes one of Australia's largest boomerang structure
The Causeway Pedestrian and Cyclist Bridges Project is a critical part of the $1.5 billion Perth City Deal and has achieved significant milestones over the past year. This transformative project will improve connectivity and safety for pedestrians and cyclists travelling between McCallum Park, Heirisson Island, and Point Fraser.
Beyond constructing two bridges, the project will enhance visitor and community experience by creating new seating areas and pause points along the river, allowing people to rest and enjoy the scenery. The project includes temporary realigning of Riverside Drive and shared-path connections and replacing a section of 100-year-old water main.
The project integrates cultural elements developed with Matagarup Elders Group to reflect local Whadjuk Noongar culture and heritage. These include bridges designed to symbolise the Waugyl (rainbow serpent), more than 700 new trees, Aboriginal sculptural art and mural installations, and wayfinding and storytelling signage.
Landscaping and design elements will enhance the City of Perth and the Town of Victoria Park whilst new lighting features will make distinctive landmarks of the bridges, promoting Perth domestically and internationally.
Early in 2024 the first bridge module, a 43-metre, 130-tonne structure was installed, this marked the start of installation of 16 modules across the river. The bridges feature three pylons representing two 47-metre digging sticks (wannas) and one boomerang (koylie) 54 metres in length, making it one of Australia's largest boomerang structures.
Manufacturing bridge components locally at Civmec's Henderson facility supports local jobs and economic growth. In the initial phase of the bridge module installation process at McCallum Park, components were transported to the three sites and installed utilising a crawler crane with lifting capacity of 1,600 tonnes - equivalent to the weight of 100 buses.
Cable installation, bridge lighting, features, deck, and riverside works are on track. The project is expected to be complete by late 2024. It will significantly improve safety, connectivity, community amenity and boost activity at McCallum Park, Heirisson Island and Point Fraser.
Key projects
PROJECT | TOTAL PROJECT COST ($ MILLION) | 2023-24 COST ($ MILLION) | COMPLETION DATE | DESCRIPTION |
---|---|---|---|---|
Goldfields-Esperance | ||||
Outback Way | 46.5 | 1.3 | Aug 2024 | Progressive sealing works. |
Metropolitan Region | ||||
Causeway Cyclist and Pedestrian Bridges | 105.9 | 70.1 | Late 2024 | Construct new pedestrian and cyclist bridges alongside the Causeway. |
Causeway Enabling Works | 84.1 | 61.7 | Late 2024 | Enabling activities and activation works. |
Wheatbelt Region | ||||
Moorine Rock to Mt Holland | 60.0 | 30.0 | Apr 2025 | Upgrade for transport of lithium. |