Community Access

Improved Community Access and Roadside Amenity

Government Goal

Strong communities

Aim

Improve personal mobility and access needs on the road network.

About the Program

The program provides infrastructure including: remote access roads; access for walking and cycling; improved access and mobility for people with a disability; integrated public transport; and improved amenities such as information bays, noise attenuation and landscaping.

Key Performance Indicators
Results
Community satisfaction with cycleways and pedestrian facilities was above our target and is consistent with last year’s result

Community satisfaction with cycleways and pedestrian facilities was above our target and is consistent with last year’s result

Percentage of the year that 100 per cent of the state Road Network was available came in under our target with a decrease from last year

Percentage of the year that 100 per cent of the state Road Network was available came in under our target with a decrease from last year

Contracts completed on budget exceeded our target showing continued strong performance

Contracts completed on budget exceeded our target showing continued strong performance

  2018 2019 2020

Program expenditure $ million

137

52

36

Looking Ahead

Works planned for next financial year include:

  • progress Matagarup Bridge activities and associated works
  • begin construction of the Coolgardie-Esperance Highway Emu Rocks section upgrade
  • continue upgrade works on remote access roads
  • improve pedestrian and cycling facilities
  • continue development of the Swan River crossings
  • continue sealing and improvements on Great Central Road between Laverton and WA/NT Border
  • commence intersection upgrades on Great Eastern Highway (Wooroloo and Sawyers Valley)
  • continue sealing and improvements on the Broome-Cape Leveque Road
  • continue improvement works on the Duncan and Gordon Downs Roads
  • commence improvement works on the Tanami Road.

Some of these are already underway; visit the Projects and Initiatives section of our website to find out more.

Key Projects

Project Total Project
Cost
($ million)
2019–20
Cost
($ million)
Completion
Date
Description

Metropolitan Region

       

Principal Shared Path – Leach Highway to Mount Henry Bridge (Mitchell Freeway)

15.4

6.5

Mid 2021

Provision of a Principal Shared Path including lighting.

Principal Shared Path – Victoria Street station to North Fremantle station (Fremantle line)

7.0

6.5

Early 2021

Provision of a Principal Shared Path including lighting.

Bridge 904 Hamilton Street – Bridge Replacement

8.1

3.2

August 2019

Replacement of existing timber bridge with a new composite concrete and steel bridge.

Hepburn Avenue Noisewall

4.7

0.9

August 2019

Construct a noisewall – near NorthLink.

Mid West – Gascoyne Region

Square Kilometre Array Access Roads and Floodways

35.0

7.7

December 2019

Construction of concrete floodway, road realignments and installation of cattle grids on access roads.

Pilbara Region

Marble Bar Road Coongan Gorge Realignment

38.6

4.2

June 2019

Marble Bar Road Coongan Gorge realignment.

Karratha-Tom Price Road – Stage 3

95.0

81.5

Late 2020

Sealing of Karratha-Tom Price Road – Stage 3.

Wheatbelt Region

Wheatbelt Secondary Freight Network

87.5

3.2

Late 2025

Upgrade significant freight route within the Wheatbelt region.

Goldfields – Esperance Region

Outback Way Upgrade

164.0

2.2

Late 2026

Sealing priority section of Outback Way.

Kimberley Region

Bidyadanga Road

4.1

0.5

Late 2020

Complete construction and seal including improving drainage, constructing a parking bay and sealing the airstrip.

Aerial view of pedestrian bridge over road Read the story

Community Access

Keeping You Moving – No Matter How You Choose To Travel